A Christmas shutdown fitout is one of the smartest ways to refresh an office or shop without losing trading days. While staff are on leave and customers are away, joinery can be installed, walls painted and floors replaced, so the business reopens in January looking new. The catch is timing: design, approvals and manufacture must be finished before suppliers and certifiers close.
SteepWood builds and installs commercial joinery from our Newcastle workshop across Newcastle, the Central Coast and Sydney. This guide covers the key 2026–27 dates, what can realistically be done, lead times and a planning checklist.
Key dates for the 2026–27 break
| Date | What happens | Source |
|---|---|---|
| Friday 18 December 2026 | NSW school summer holidays start (Eastern division) | NSW Department of Education |
| Friday 25 December 2026 | Christmas Day | NSW Government |
| Saturday 26 December 2026 | Boxing Day | NSW Government |
| Monday 28 December 2026 | Additional public holiday for Boxing Day | NSW Government |
| Friday 1 January 2027 | New Year's Day | Fair Work Ombudsman |
| Friday 8 January 2027 | NSW public service Christmas closedown ends | PSA |
| Wednesday 27 January 2027 | School holidays end (Eastern division) | NSW Department of Education |
The HIA notes that an annual Christmas shutdown is industry practice in residential building, so many trades and suppliers close for part of this period. Check each supplier's dates early.
What can be done during a shutdown
| Works | Shutdown friendly? | Why |
|---|---|---|
| Joinery install (reception, kitchenette, storage) | Yes | Built in advance, installed in days |
| Painting and minor patching | Yes | Short and quiet in an empty space |
| Carpet tiles or vinyl | Yes | Easier with furniture moved out |
| Retail display and counter refit | Yes | Store closed or quiet trading |
| New partitions and ceilings | Sometimes | Needs approvals and more trades |
| Major services changes | Rarely | Trades and certifiers limited |
| Full strip-out and rebuild | No | Too long for a two-week window |
Working back from the shutdown
Joinery has to be designed, approved and built before the break. Progressive Corporate puts design and approvals at six to ten weeks for small offices before construction starts. For a joinery-only refresh, the sequence is shorter but still needs planning.
- Scope and measure: Agree what will change and measure the site.
- Quote and approval: Itemised quote signed off.
- Shop drawings: Drawings approved by you and the building manager or centre.
- Materials ordered: Board, hardware and benchtops ordered before suppliers close.
- Manufacture: Built in the workshop.
- Install window booked: Dates confirmed in writing.
If you are reading this in early December, a full fitout over this break may be too tight, but a smaller joinery install may still be possible. Talk to us now, or plan for the next quiet period. Our office fitout timeline guide explains each stage in more detail.
STEEPWOOD COMMERCIAL JOINERY — Joinery built ahead of the break and installed while your office or shop is closed, across Newcastle, the Central Coast and Sydney. Explore commercial joinery or Get a free measure and quote.
Shutdown ideas by business type
| Business | Shutdown project |
|---|---|
| Professional office | New reception counter and kitchenette |
| Medical or dental clinic | Consult room cabinetry and reception refresh |
| Retail shop | New counter and display wall before January sales end |
| Cafe | Servery and back bar refresh during a planned closure |
| Salon or barber | New stations over a short closure |
| Warehouse office | Storage walls and lunchroom upgrade |
Penalty rates and costs
Work on public holidays usually costs more because of award penalty rates, and fewer trades are available. Most shutdown works are scheduled on the normal weekdays between public holidays, such as 29 to 31 December, or in the first weeks of January. Building managers may also restrict works on public holidays.
Building and centre rules over the holidays
- Building managers: Confirm access, security and lift bookings over the break.
- Shopping centres: Many centres restrict works during peak Christmas trade; ask for the centre's blackout dates.
- Insurance: Make sure certificates are current for the works period.
- Security: Plan who opens and locks up the site.
Regional notes
- Newcastle and the Hunter: Many office tenants are moving into upgraded space. See our Newcastle office fitout guide.
- Central Coast: Gosford and Erina tenancies often refit in the January quiet period. See our Central Coast commercial joinery guide.
- Sydney: Building rules and loading docks need early booking. See our small office fitout Sydney guide.
Planning checklist
- Measure the space and photograph existing joinery.
- Agree a fixed scope and budget.
- Get itemised quotes for joinery and other trades.
- Sign off shop drawings.
- Request building manager or centre approval.
- Confirm install dates and access in writing.
- Arrange furniture moves and IT disconnection.
- Plan staff communication for the return date.
For larger fitouts, see our office fitouts and shopfitting pages.
SteepWood is Pavit Pty Ltd trading as SteepWood, ABN 52 697 313 269, NSW Carpentry Contractor Licence 489553C, with $20 million public liability and a 10-year structural warranty on joinery.
Frequently asked questions
Can a fitout be done over the Christmas shutdown?
Yes, smaller fitouts and joinery installs can be done while an office or shop is closed. The key is to finish design, approvals and manufacture beforehand, because suppliers, certifiers and many trades also close over the break.
When is it too late to plan a Christmas shutdown fitout?
For the 2026–27 break, design and joinery orders generally need to be locked in during November or early December. If that window has passed, plan for the next quiet period, such as Easter or the June to July school holidays.
What are the NSW public holidays over Christmas 2026?
In NSW, Christmas Day is Friday 25 December 2026, Boxing Day is Saturday 26 December with an additional public holiday on Monday 28 December, and New Year's Day is Friday 1 January 2027.
Is work over the holidays more expensive?
Work on public holidays usually costs more because of penalty rates, and fewer trades are available. Scheduling work on normal weekdays between the public holidays, or in early January, often keeps costs reasonable.
What should I do now to prepare for a January refit?
Measure the space, agree the scope, get itemised quotes, sign off shop drawings, request building or centre approvals and confirm delivery and install dates in writing before suppliers close.
Book your shutdown or January refit
Send us your floor plan, photos and the dates your business will be closed. We will tell you what is realistic for this break, what fits the next quiet period and price the joinery item by item. Get a free measure and quote or call 0468 387 676.